Advertising structures such as billboards, unipoles, and pylon signs generally require a Building Approval (PBG) under Government Regulation 16/2021. Applications are made online via SIMBG with applicant data, land data, architectural drawings, and structural calculations, followed by payment of the PBG levy (SKRD).
Steps
Confirm whether PBG is needed
Make sure your type and size of advertising structure requires a PBG under local rules.
Prepare technical documents
Site plan, structural/architectural drawings, structural & foundation calculations by a qualified engineer, and material specifications.
Register & fill in data on SIMBG
Create a SIMBG account, enter applicant and land data, and upload the technical documents.
Consultation with the TPA/TPT
Documents are reviewed by the expert/technical assessment team. Revise if there are notes.
Pay the PBG levy
Once the technical standards are met, the levy is calculated and paid according to the SKRD.
PBG issued
The PBG is issued. The structure can be built according to the approved drawings, followed by the advertising permit and tax.
Documents usually required
- Applicant data (ID card, NIB/deed, tax ID)
- Proof of land ownership/rights or a land lease agreement
- Site and location plan
- Advertising structure drawings
- Structural & foundation calculations (signed by a qualified engineer)
- Technical material specifications
What is a PBG?
A Building Approval (Persetujuan Bangunan Gedung, PBG) is the permit issued by the local government to build, alter, extend, or maintain a building according to technical standards. PBG replaced the IMB since Government Regulation No. 16 of 2021 came into force.
Does every advertisement need a PBG?
No. Small name signs mounted on a shop wall usually do not need a separate PBG. A PBG is usually required for structural advertisements — ground-mounted billboards, unipoles, pylon signs, or rooftop signs on steel frames. The thresholds follow local rules.
Common mistakes
- Building the structure first and getting the permit later → risk of dismantling
- Structural calculations without a qualified engineer → rejected during verification
- Unclear land data (no lease agreement) → delays
How we help
We prepare the technical drawings and structural calculations, and assist the SIMBG application until the PBG is issued — while also producing and installing the structure.
This guide is general in nature. Requirements, zoning, and rates may differ in each regency/city according to the applicable local regulation. Contact us to check the rules at your location.